EHB Allows Mariner East 2 Pipeline Construction To Resume At 16 Of 55 Sites

The Pittsburgh PowerSource and StateImpact Friday reported the Environmental Hearing Board this week agreed with a request by Sunoco to allow a resumption of construction on the Mariner East 2 Pipeline at 16 of the 55 sites the EHB shut down on July 25.
The EHB Friday extended the ban on further construction at the remaining sites until August 9 when a hearing could be held involving the 3 environmental groups seeking further extension of the construction ban.
A hearing on the merits of appeal of the permits issued by DEP for the pipeline are still some months off.
Click Here for EHB documents related to this case (Case #2017-009).
NewsClips:
Related Stories:

0 Response to "EHB Allows Mariner East 2 Pipeline Construction To Resume At 16 Of 55 Sites"

Post a Comment

Iklan Atas Artikel

Iklan Tengah Artikel 1

Iklan Tengah Artikel 2

Iklan Bawah Artikel