EHB Again Denies Temporary Supercedeas In Appeal Of Mariner East 2 Pipeline Permits
The Environmental Hearing Board Thursday denied a second request for a temporary supercedeas and an expedited hearing by environmental advocacy groups appealing DEP’s issuance of 20 permits for Sunoco’s Mariner East 2 natural gas liquids pipeline.
A temporary supercedeas would have prevented Sunoco from beginning construction of the pipeline until the merits of the case were decided. Sunoco is still waiting for additional permits for the project from the U.S. Army Corps of Engineers.
In an opinion denying the request, the Board said the appellants did not present any information not previously considered by the Board to justify reconsideration of the decision not to grant the supersedeas.
A copy of the EHB decision is available online.
A full hearing on the supercedeas request is scheduled to begin on March 1.
Click Here for copies of documents filed as part of the appeal.
The Department of Environmental Protection published notices in the February 25 PA Bulletin giving formal public notice they issued the county by county permits for the Mariner East 2 Pipeline Project (starting on page 1212).
NewsClip:
EHB Denies Latest Call To Halt Mariner East 2 Pipeline Construction
Click Here for copies of documents filed as part of the appeal.
The Department of Environmental Protection published notices in the February 25 PA Bulletin giving formal public notice they issued the county by county permits for the Mariner East 2 Pipeline Project (starting on page 1212).
NewsClip:
EHB Denies Latest Call To Halt Mariner East 2 Pipeline Construction
Related Stories:
EHB Denies Supercedeas In Appeal Of Mariner East 2 Pipeline PermitsAltoona Mirror: PUC Faces Major Decision On Reversing Flow Of Buckeye Laurel Pipeline